Deputy Director of the Special Construction of Russia A.Mordovets: "The term for the completion of the construction of the Vostochny cosmodrome is unchanged - June 2015"

Already next year, the Vostochny cosmodrome under construction should become the operating starting complex. The first launch of missiles from the East is planned for 2015 year, the first manned launch - for 2018 year. The construction is closely focused on the leadership of the country. Compliance with the timing of the launch is at a special state control.

Deputy Director of Spetsstroy of Russia Alexander Mordovets in an interview with the Interfax-Dalniy Vostok news agency stated the following: “Work on all objects of the cosmodrome is progressing at an increasing pace. After Russian President Vladimir Putin visited the cosmodrome in September, the issuance of design documentation went faster. This is an important moment in our work, the pace of construction has noticeably accelerated.

In particular, 1,28 thousand tons of reinforcement skeletons were installed, over a thousand tons of metal structures, almost 2 thousand square meters of enclosing structures, more than 7,6 thousand cubic meters of concrete were laid during the erection of monolithic structures, almost 16 thousand square meters of roofing were completed, area 19 thousand square meters. By the end of the year 90% of the roads will be in asphalt concrete.

Of the 13 facilities at a 30% completion stage, we already have the first stage of the first stage of the railway and the railway station; on October XNUMX, we are already transferring facilities for temporary operation to TsENKI. In addition, the work on the first stage road has been completed. "

Compliance with the construction schedule is somewhat complicated by problems with personnel, the unresolved issue of the northern surcharges, the need to look for new subcontractors instead of those who proved unreliable.

Nevertheless, A. Mordovets is absolutely sure that the deadlines for the commissioning of the cosmodrome will be met: “Now the cosmodrome is about 70% ready in terms of performance of work by Spetsstroy. (…) In any case, the deadline is June 2015, which is unchanged for us, we are focused only on it ”.