In the Khabarovsk Territory, the number of applications for technological connection increased by a factor of 1,5

For 7 months of 2014, Khabarovsk Electric Networks, a branch of JSC DRSK (part of RAO ES of the East) received more than 2300 applications for technological connection of facilities of all categories of consumers, which is almost 1,5 times higher than the same indicator in 2013 , the press service of the energy company said

To implement the connection of the applicants, the DRSK, by the end of the year, plans to build and reconstruct more than 40 km of 0,4-10 kV power transmission lines in the Khabarovsk Territory, and put into operation 150 new transformer substations (TP).

The most actively requested to connect to the power grid are legal entities that need the power of power receivers up to 150 kW and those connecting residential buildings up to 15 kW. This preferential group of applicants often fails to fulfill the terms of the contract for technical connection, while the network organization is obliged to construct power facilities for connection as quickly as possible (during 4-6 months), to extend power lines. The main cause of this problem is the unavailability of the construction objects themselves, which are subject to connection to the power grids. Thus, the power company diverts funds for the construction of facilities that are not in demand. It would be much more effective to invest the spent investment funds in the reconstruction of the network equipment of the settlements of the Khabarovsk Territory, where there are acute problems with the quality and reliability of the power supply.

It should be particularly noted that in the event that the applicants do not fulfill the preferential category of the terms of the contract for technological connection, the DRNC has the right to recover from the applicants the real costs for the construction of unclaimed networks that are many times greater than the payment for technological connection. The experience of such penalties at the network organization is available.

- But there is one more nuance. The Government of the Russian Federation has prepared a number of legislative normative acts that significantly reduce the cost for applicants and shorten the process of technological connection, - says the head of the service for prospective development and technological connection, Yuri ZHURAVLEV. - The term for technological connection in the near future should not exceed 40 days from the date of the contract. In this case, the excitement of the population with the submission of applications for the future is incomprehensible, if in the near future it will be possible to connect an already built facility cheaper and faster, and most importantly, without the risk of paying the network organization the real cost of building networks.

Therefore, the population should not give in to panic, but realistically assess the time frame for the construction of its facilities and submit applications within the time required for them.

Today, the cost of technological connection up to 15 kV for consumers not falling into the preferential group is 12960 rubles, for individual entrepreneurs connecting objects up to 150 kW - 5195,96 rubles per kilowatt.