Equipment for grinding ore was installed at MMC Udokan in Transbaikalia

Equipment for grinding ore was installed at MMC Udokan in Transbaikalia
Photo: press service of the company "Udokan Copper"

In the Trans-Baikal Territory, Udokanskaya Med 'has completed the installation of equipment for grinding ore. The building of the last sixth mill was assembled at the construction site of MMC Udokan.

According to the press service of the government of Transbaikalia, all that remains is to install attachments and auxiliary equipment, electric motors and monitoring and control systems at the mills.

Pre-crushed ore at the Zapadny open pit will be transported here in fractions of less than 300 mm via belt conveyors. Six mills grind the ore down to fractions of less than 170 microns. Such raw materials, in turn, will enter the flotation line. At the first stage, the processing capacity will be 12 million tons of ore per year.

According to the general director of the company "Udokanskaya Med" German Mironov, by the end of the year it is planned to complete the entire volume of concrete work. Also, the installation of technological equipment will be almost completed and part of the tests will be carried out.

 