In Primorye, 30% of the work was carried out as part of the national project of the BKAD for 2020

In Primorye, 30% of the work was carried out as part of the national project of the BKAD for 2020
Photo: primorsky.ru

A six-kilometer stretch of road to the village of Tavrichanka in the Nadezhda district of Primorye will be finished in July. This is two months ahead of schedule.

The road to Tavrichanka has long been in need of repair. Last year, two kilometers were repaired in the national project “Safe and High-Quality Roads”, and in 2020, six more kilometers will be repaired. The contractor has almost completed the laying of asphalt, work is ongoing on the last site. Total will replace 49 thousand square meters. meters of road surface.

The chief engineer of the contractor - SPETSSU JSC, Ivan Zaichenko, said that the builders had to remove old soil that could not "hold" the asphalt, rocky soil was poured into its place, which was compacted with rollers and covered with gravel. Asphalt was laid out in three layers: leveling, lower and upper. It is necessary to make roadsides, to establish signs, to equip stops, to mount a rail in separate sections. Despite a significant amount of repair, the road workers are ahead of schedule.

One of the main requirements for the contractor is the quality of the repair. There is special equipment for these purposes, including the latest core sampler designed for sampling and measuring asphalt.

As Ilya Matyushko, Deputy Head of the Control and Acceptance Department of KSCU Primimptodor explained, the work is checked in stages: from the moment of excavation of the foundation pit to eliminate abysses. After that, they give the green light to the next stage - backfilling of rock.

So, after checking the quality of work on the Nakhodka-Lazo-Olga-Kavalerovo road section, the contractor had to cut off almost two km of the surface layer of the asphalt pavement and lay new asphalt.

In total, this year in the Primorsky Territory, as part of the national project of the BKAD, about 60 objects with a total length of 83 km will be brought into normative state. A number of streets in Artyom have already been repaired, and the first object is the road to the Vladivostok airport, the builders finished a month ago. As part of the implementation of these tasks, about two billion rubles were spent.