Temporary storage warehouses began to be built for the Blagoveshchensk-Heihe bridge

Temporary storage warehouses began to be built for the Blagoveshchensk-Heihe bridge
Photo: amurobl.ru

For the full-fledged operation of the Blagoveshchensk-Heihe cross-border bridge, a customs and logistics terminal will be built in the Amur Region. However, first there will be built temporary storage warehouses. The work has already begun.

According to the temporary scheme, warehouses and parking lots of vehicles will be placed there. It is planned to complete the construction of temporary storage warehouses by the end of August. Now 25 pieces of equipment and 50 workers are working at the construction site. At the same time, their number will gradually increase.

The terminal itself with an expanded warehouse area will be built later in four stages. In conclusion, by 2023, it is planned to create a railway terminal in the village of Berezovka. The total volume of buildings will be about 97 thousand square meters. meters, an area of ​​110 thousand square meters. meters will occupy warehouses and parking. The volume of investments in the project will amount to 7,6 billion rubles. It will also allow the creation of 275 new and 225 related jobs.

Within the framework of the project of the border bridge crossing, they create a site for the future toll point. Builders are equipped with four lanes for collecting fees: two for freight and two for passenger vehicles. Two buildings and a technological tunnel are already ready. By July 31, work should be completed in full.

Now a temporary checkpoint is operating in the area of ​​the bridge. The design of the capital building is already underway; it is planned that it will be ready in 2022. The bridge itself will work after removing all restrictions imposed due to the coronavirus pandemic.