Rosneft completed the construction of a linear part of a pressure pipeline with increased capacity to transport oil from the Srednebotuobinsky oil and gas condensate field

The construction of the oil pipeline "Srednebotuobinskoye NGKM - TS ESPO" is being implemented within the second stage of the enterprise development.

Rosneft completed the construction of a linear part of a pressure pipeline with increased capacity to transport oil from the Srednebotuobinsky oil and gas condensate field
According to the press service of Rosneft, LLC Taas-Yuryakh Neftegazodobycha, a subsidiary of NK Rosneft, completed the construction of the linear part of the increased-pressure pipeline.

The new pipe has a diameter of 530 mm, capacity of 5 million tons of oil per year, and the length of the new pipeline is 168 km. The new system will connect the fields near the city of Lensk (Yakutia) with the pipeline system "Eastern Siberia - Pacific Ocean" (ESPO).

The project envisages an increase in annual production to 5 million tons, as well as expansion of the existing central oil collection point and delivery point with a tank farm with a total volume of 70 thousand m X NUMX.

It is reported that construction and installation work has been carried out since November 2015 of the year and completed as planned.