The working group of the government of Chukotka estimated the construction of the reservoir dam in Perveka

A working group of the Government of the Chukotka Autonomous Region under the leadership of Valery Vasilyev, Head of the Industrial Policy, Construction and Housing and Public Utilities Department, visited the dam of the reservoir of Pevek, where reconstruction of the hydraulic structure is underway. The delegation included representatives of executive authorities, government agencies and contractors, the press service of the head of the region said.

As the Deputy Head of the Department Valery Kozlov, who joined the local monitoring group, stated, at present, the facility is taking steps to prepare the dam body for laying a waterproofing layer consisting of a special polymer film.

- Excavation works are carried out by the contractor Teploenergoservice DKM. The Chukotka miners' artel is subcontracted, which is a reliable performer of the assigned tasks. These activities are planned to be completed by November-December of this year. If all the work is completed on time, then by the fall of 2015 Pevek will be fully provided with water, '' said Valery Kozlov. - Also, a residential complex for specialists is being arranged on site. This should increase the efficiency and productivity of the work shift.

Valery Kozlov noted that on-site daily monitoring of work progress is carried out, including with the preparation of photo reports and fixation of the amount of equipment employed at the facility, the volume of displaced soil. To date, the site has three units of heavy machinery, four loaders and dump trucks, which deliver the soil for laying the dam body.

As Roman Kopin, Governor of the Chukotka Autonomous Region, commented, it is very important not to delay the work and complete the reconstruction of the hydraulic structure on time.

- The Pevek reservoir has been providing water to the population of the city for more than 40 years, this is the most optimal way of water supply. The Government of the region faces an important task to complete the reconstruction of the facility as soon as possible and with high quality. The latest technologies are used in the works to solve this problem, but at the same time, specialists should make maximum efforts to restore the traditional water supply of the city, Roman Kopin emphasized.

At present, the desalination plants satisfy the drinking water needs of the residents of Pevek and the city’s organizations. In addition, water is delivered by machines from alternative sources.

Financing of work on the hydraulic structure is carried out within the framework of the state program "Development of the infrastructure of the Chukotka Autonomous Okrug for 2014-2018".