The second section of the Vladivostok-Nakhodka route in July will be sent for examination

Alexei Shirshov, director of the Primorsky Territory Road Management Department, said that on July 4, the project of the second section of the Vladivostok-Nakhodka highway, from 18 to 40 kilometers, will be sent for state expertise. The conclusion will be received by the end of August.

Currently, the work is carried out on the first section with 0 to 18 kilometer. Alexey Shirshov noted that the schedule of work is fully complied with. Completion of construction is planned for the first quarter of 2016 year.

On the third stage from 40 to 146 kilometers, the documentation on the planning of the territory is being developed.

The construction of the Vladivostok-Nakhodka-Vostochny port highway will improve the service of the increased freight traffic in this direction. The speed limit will increase, due to which the travel time will be noticeably reduced. At the same time, the transport shoulder Vladivostok-Nakhodka will decrease by 15 kilometers.