The first objects of the factory "Inaglinskaya-2" in Yakutia will pass in a year

Special project Coal of the East of Russia

In Yakutia, the Inaglinsky mining and processing complex of the Kolmar coal mining company is actively building the Inaglinskaya-2 processing plant with a capacity of 12 million tons of coal per year. The company plans to hand over the first-stage facilities — the main building of the factory, the administrative building, the loading point, galleries, warehouses of finished products and ordinary coal — in April, the company plans on 2020.

Now on the construction site, metal structures of the main building are being mounted, reinforced concrete slabs for the installation of process equipment are being installed. According to the press service of “Colmar”, the metal structures of the administrative and household building have already been mounted, the specialists have begun to install walling walls.

“The project for the construction of the largest in the Far East concentration plant" Ignalina-2 "involved more than 200 people from the construction and assembly department of the company" Kolmar ". Even more 200 people are from contracting organizations that perform the vertical layout of the site and the construction of a warehouse of finished products, ”commented Artem Levin, General Director of Colmar.

A cold-built arched-type warehouse and two warm-built warehouses were built at the site, the fire station metalwork is being installed, a parking garage in the block with a warehouse and a temporary boiler room were built.