The main equipment is delivered to the construction site of Blagoveshchenskaya CHPP on schedule

Blagoveshchenskaya CHPP (the customer-developer of the second stage of the facility of the same name, subsidiaries and dependent companies of JSC RusHydro, managed by JSC RAO Energy Systems of the East) continues to accept the main power equipment for the construction of the second stage of the plant of the same name. In accordance with the approved delivery schedule, the general contractor of the construction site, Power Machines, delivered the main units of the turbine generator to the installation site.

Another bulky cargo - a generator stator weighing 122 tons - was delivered on a special railway platform to the turbine shop of the Blagoveshchenskaya CHPP. A month earlier, a 39-ton generator rotor was delivered to the construction site.

Despite the low temperatures, work on construction sites continues. More than 300 people and 30 pieces of equipment work daily. In the boiler room, the installation of the boiler unit and auxiliary equipment continues.

To date, more than 430 tons of boiler metal structures have been assembled. In the turbine shop, the work on concreting the columns was completed, scaffolding was installed for the installation of formwork for the upper structure of the turbine unit foundation. At the construction site of the cooling tower, the third, final stage of concreting the foundations of the tower frame is being carried out. The delivery of the cooling tower steel structures is expected in January.

At the beginning of next year, power transformers will be shipped from St. Petersburg from the joint venture of the general contractor and the Toshiba corporation to the Blagoveshchenskaya CHPP.

Phase 2 of the Blagoveshchenskaya CHPP is one of four projects of the investment program of JSC RusHydro for the construction of new power facilities in the Far East, implemented jointly with JSC RAO Energy Systems of the East in accordance with the Decree of the President of the Russian Federation. For these purposes, 50 billion rubles have been allocated from the budget of the Russian Federation. Comprehensive management of the activities of all subsidiaries and dependent companies of RusHydro (customers-developers), created specifically for the construction of thermal generation facilities in the Far East, is carried out by RAO Energy Systems of the East (part of the RusHydro Group).