On Kolyma the first support of a high-voltage line for the development of gold deposits

In the Khasynsky district of the Magadan region, the first support of the 220 kilovolt overhead line "Orotukan - Palatka - Central" was installed. JSC DVEUK has been building a high-voltage line with a length of 377 km since November last year.

By the forces of the general contractor organization of Yakutskoye LLC, 920 thousand square meters of clearings were cut, 3 190 running meters of wells were drilled with the subsequent installation of piles, 552 cubic meters of foundations were installed on the pedestrians, 106 supports were assembled and the first one was installed, the press service of the Ministry of Energy a reference to the director of the Directorate for the Construction of Power Facilities in the Territory of the Magadan Region, OAO DVEUK, Dmitry Chernykh.

According to him, the completion of the project in 2015 will ensure the delivery of the power of the Ust-Srednekanskaya hydroelectric power station under construction to the southern part of the Magadan region, thereby unloading the electric grid in the direction of Kolyma HPP - Ust-Omchug-Magadan. This will additionally transfer about 60 megawatt of electrical power for the development of the deposits of the Yano-Kolyma gold province. In addition, at 10 megawatts, losses will be reduced when transporting power at the Central Energy Center of OJSC Magadanenergo.

Recall that the project of power grid construction is included in the investment agreement on cooperation for 2014 year between the government of the Magadan Region and JSC DVEUK, as well as the current version of the federal targeted program "Economic and Social Development of the Far East and the Baikal Region for the period up to 2018."

The state customer of the project is the Ministry of Energy of Russia.