Housing readiness for flood victims in the Amur region - 67,9%

The degree of housing readiness for victims of flooding in the Amur Region is 67,9%, Deputy Chairman of the Government of the Region Alexander Zhitkov told the First Deputy Chairman of the Government Vera Shcherbine at a working meeting. In total, by July 14 it was planned to build 173 residential premises with a total area of ​​10 335 square meters. m for 521 person.

The difficult situation is in Chigiry, where the contractor refuses to subcontract other organizations. Alexander Zhitkov expressed concern that the contractor on his own might not have time to hand over the houses within the deadlines set by the President of the country. Despite the fact that the contractor did not conclude the contract with the municipality, but directly with the affected citizens, the Regional Government is taking measures to increase the pace of construction, daily monitoring of the work of the builders is being carried out, support is being provided for the delivery of construction materials.

To date, a total of 32 houses have been built in the region. In addition, 79 more houses are being built with the money collected by Channel One as part of the Whole World campaign.

"Absolutely inappropriate the word" impossible. " Everything should be built in a timely manner. For this we must take all measures, "Vera Shcherbina stressed once again.