FGC requires a transformer to a substation in the Amur region

FGC UES has announced an open one-stage tender for the right to conclude an agreement for the supply and installation of a transformer at the 220 kV Klyuchevaya substation (Amur Region) for the Pokrovsky Rudnik OJSC transformer substation (part of the Petropavlovsk group), according to the procurement site.

The organizer of the competition is Energostroysnabkomplekt UES, JSC. The initial (maximum) price of the contract is 253,026 million rubles. In accordance with the tender documentation, the transformer capacity must be equal to 25 MVA.

Currently, the Klyuchevaya substation uses one 20 MVA transformer and one 4 MVA transformer.

The delivery of equipment should be completed in March 2016 year, commissioning - May 2017 year.

Applications for participation in the competition are accepted until August 18, the results are scheduled for September 18.